Thursday, 21 February 2013

Formation update and sketching plans

Formation work is progressing well, with the ground looking almost ready for some ballast.

At the north, drains are still being installed
Drains are also still being installed at the south end of the platform
South of the platform, the formations look almost finished
Seats and other station furnishings have appeared
Some more work has finally been done on the carpark, with a footpath appearing behind the station building
I was also lucky enough to be sent some staging (planning) diagrams by project manager Aiman Grace, who has given me permission to post them here.

The final track layout, both on its own and overlaid on the old layout
Stages 1 and 2: installing additional crossovers and cutting back the east loop
Stage 3: removing the old yard and signalling commissioning
Stage 4: Platform 3/4 construction
Stage 5: Platform 2 constrction
Stage 6: Mainline construction and finalisation works