Tuesday, 26 March 2013

Pre-Easter shutdown

With Easter approaching, preparatory works have almost finished, with as much track as possible laid and ballasted. Very little actually needs to be done over the weekend.

New tracks laid through the station. Since this photo was taken much of the track has been ballasted
Track at the north end ready to be connected
The tamper group parked up
From what I can tell, all that needs doing over the long weekend is to connect the track and move the ticket machine back to its original location, and possibly some minor touchups - and then the upgrade is complete.

Before and after photos will be posted next week.

1 comment:

  1. Looking good Alex. The Signalling has all been tested off-site last week and ready to go over this weekend.

    ReplyDelete